Question 1: Which of the following is NOT a distinguishing characteristic of a project?

A:A: Unique

B:B: Community

C:C: Temporary

D:D: Creates value

Question 2: An energy company has identified a number of initiatives including building new plants, drilling new wells and exploring new areas. They would like to manage these in a coordinated way for maximum benefit. What is the best term to describe this?

A:A: A portfolio

B:B: A project

C:C: A program

D:D: An operation

Question 3: Which of the following is NOT a responsibility of a project manager?

A:A: Managing the schedule

B:B: Managing the budget

C:C: Managing team performance

D:D: Sponsoring the project

Question 4: Which of the following is TRUE about a Program?

A:A: A Program is a group of related projects

B:B: A Program is a group of unrelated projects

C:C: Programs are ongoing

D:D: Programs create business value directly

Question 5: Which of the following is NOT true about portfolio management?

A:A: A portfolio is a collection of projects

B:B: A portfolio supports strategic business objectives

C:C: A portfolio may contain programs

D:D: A portfolio is always a group of programs

Question 6: A project manager’s team is not reporting problems to him because of his bad temper. The best thing the project manager could do would be:

A:A: Apologize to the team members

B:B: Look for a new job

C:C: Improving his interpersonal skills

D:D: Get anger management counseling

Question 7: Which of the following is NOT a project constraint?

A:A: Time

B:B: Scale

C:C: Budget

D:D: Scope

Question 8: A data center is being constructed that will house 500 servers. The servers can be installed before the construction is completed. Which project constraint is LEAST affected?

A:A: Cost

B:B: Scope

C:C: Time

D:D: Quality

Question 9: Which of the following is NOT an example of operational work?

A:A: Building a purchase order systemCorrect Answer

B:B: Processing purchase orders

C:C: Maintaining a purchase order system

D:D: Improving a purchase order system

Question 10: A project manager is trying to get an accountant to complete training he does not want to do. What is the BEST approach for the project manager?

A:A: Refuse to work with him because he is being difficult

B:B: Appeal to the accountant’s manager and ask to have him required to take training

C:C: Get a special dispensation so that the accountant doesn’t have to go to the training

D:D: Work with him to understand his concerns and do what you can to help alleviate them without compromising your project

Question 11: Your manager asks you where to find a list of projects that should be managed together. What is the BEST place to find this information?

A:A: Project plan

B:B: Project charter

C:C: Portfolio charter

D:D: Program charter

Question 12: You want to know specifically which business goal a group of projects and programs is going to accomplish. Which is the BEST place to look for this information?

A:A: Project plan

B:B: Project charter

C:C: Portfolio charter

D:D: Program charter

Question 13: A project manager is having trouble getting customer feedback on her project. Even though she knows the product won’t be complete for several months, the company guidelines say she should release an early version and get feedback from end users. Which type of development approach is the guideline suggesting?

A:A: Hybrid

B:B: Overlap

C:C: Agile

D:D: Predictive

Question 14: In which phase of a project is there the highest risk and uncertainty?

A:A: Starting the project

B:B: Organizing and preparing

C:C: Executing the work

D:D: Closing the project

Question 15: The transition between phases in a project is typically marked by a review of work and project performance. What is this review called?

A:A: Kill point

B:B: Phase review

C:C: Status meeting

D:D: Retrospective

Question 16: Only a project has ____________.

A:A: Initiation Processes

B:B: Closing Processes

C:C: Planning Processes

D:D: Executing Processes

Đáp án đúng:

1.A, 2B, 3D, 4A, 5C, 6D, 7B, 8C, 9A, 10D, 11A, 12B, 13B, 14A, 15B, 16A